Project critical path

Find earliest and latest timings, slack and critical tasks in a dependency network.

Your starting point

LOCAL · PRIVATE

Sample values are filled in. Change them to make this your own.

Keep the header row. Separate values with commas; quote values containing commas.

A little more clarity

RESULT

Your result will appear here.

Run the sample to see how it works.

FROM INPUT TO ANSWER

Use this tool

  1. Give every task a unique ID and duration in days.
  2. List prerequisite IDs with | between them; leave Dependencies empty for starting tasks.
  3. Calculate and review zero-slack tasks and the complete timing table.
WHAT THE NUMBERS MEAN

Reading your result

Earliest/latest timings are measured from project day zero. Slack is permissible delay without extending this model’s finish. Multiple parallel critical branches may exist.

UNDER THE HOOD

How this works

Forward pass finds earliest start/finish; backward pass finds latest start/finish; zero-slack tasks are critical.

Use the units shown beside each field. For monetary amounts, use one currency throughout; calculations do not convert currencies. Results normally display up to two decimal places. Nonzero values below 0.01 use up to six significant digits; values below 0.000001 use scientific notation (for example, 1E-7 means 0.0000001). Rankings use unrounded values, so displayed scores can look equal without being tied. CSV downloads retain numeric precision. Monetary rounding uses half-away-from-zero. Inputs or results beyond supported precision are rejected.

Method reference: PMI, Scheduling 101.

BEFORE YOU USE THE RESULT

Assumptions & limits

Finish-to-start links only, no lag or resource constraints. Cycles, duplicate IDs and missing dependencies are rejected.

CSV inputs support quoted commas, doubled quotation marks and quoted line breaks. Headers are case-sensitive; a maximum of 500 data rows and 200,000 characters applies per table.

Results are planning aids based on the values you enter. Check important decisions and documents before using or sharing them.