Make a workable team delivery plan

Separate uncertainty, dependency timings and people availability before committing to a deadline.

Tools do not automatically transfer your results or save inputs. The linked case presets are fixed demonstration data.

Before you begin

Small project teams coordinating a short delivery

STEP 1 / 3

Describe uncertainty first

The three estimates give about 4.33 days expected duration and a one-day standard deviation for one uncertain task. This is a separate estimation exercise, not a probability of finishing the whole network.

Try the example in PERT three-point estimate ↗
STEP 2 / 3

Inspect the dependency network

Brief → Build → Release takes seven elapsed project days. Review has one day of slack. The network uses supplied working durations and has no holiday calendar or resource leveling.

Try the example in Project critical path ↗
STEP 3 / 3

Check people capacity separately

The heuristic assigns 18 hours to Ada and six to Sam. Neither exceeds the supplied period capacity. This separate workload check does not automatically prove the seven-day dependency schedule is feasible.

Try the example in Team workload allocation ↗

Make the handoff explicit

Review the assumptions before adapting these figures. A calculated result is not an order, invitation, accepted quotation or guaranteed deadline. Save your own copy before leaving; no work is stored automatically.

Read the complete worked case ↗