Project critical path
Find earliest and latest timings, slack and critical tasks in a dependency network.
Your starting point
LOCAL · PRIVATESample values are filled in. Change them to make this your own.
A little more clarity
RESULTYour result will appear here.
Run the sample to see how it works.Use this tool
- Give every task a unique ID and duration in days.
- List prerequisite IDs with | between them; leave Dependencies empty for starting tasks.
- Calculate and review zero-slack tasks and the complete timing table.
Reading your result
Earliest/latest timings are measured from project day zero. Slack is permissible delay without extending this model’s finish. Multiple parallel critical branches may exist.
How this works
Forward pass finds earliest start/finish; backward pass finds latest start/finish; zero-slack tasks are critical.
Use the units shown beside each field. For monetary amounts, use one currency throughout; calculations do not convert currencies. Results normally display up to two decimal places. Nonzero values below 0.01 use up to six significant digits; values below 0.000001 use scientific notation (for example, 1E-7 means 0.0000001). Rankings use unrounded values, so displayed scores can look equal without being tied. CSV downloads retain numeric precision. Monetary rounding uses half-away-from-zero. Inputs or results beyond supported precision are rejected.
Method reference: PMI, Scheduling 101.
Assumptions & limits
Finish-to-start links only, no lag or resource constraints. Cycles, duplicate IDs and missing dependencies are rejected.
CSV inputs support quoted commas, doubled quotation marks and quoted line breaks. Headers are case-sensitive; a maximum of 500 data rows and 200,000 characters applies per table.
Results are planning aids based on the values you enter. Check important decisions and documents before using or sharing them.