INVENTED TEACHING CASE

Make a workable team delivery plan

Separate uncertainty, dependency timings and people availability before committing to a deadline.

This is an invented scenario for learning, not a customer story. All amounts use one unspecified currency.

The question to resolve

A transparent estimate and a resource check, not a guaranteed delivery date.

STEP 1 / 3

Describe uncertainty first

The three estimates give about 4.33 days expected duration and a one-day standard deviation for one uncertain task. This is a separate estimation exercise, not a probability of finishing the whole network.

See the exact demonstration inputs
optimistic
2
likely
4
pessimistic
8
Load this case into PERT three-point estimate ↗
STEP 2 / 3

Inspect the dependency network

Brief → Build → Release takes seven elapsed project days. Review has one day of slack. The network uses supplied working durations and has no holiday calendar or resource leveling.

See the exact demonstration inputs
items
ID,Days,Dependencies
Brief,2,
Review,3,Brief
Build,4,Brief
Release,1,Review|Build
Load this case into Project critical path ↗
STEP 3 / 3

Check people capacity separately

The heuristic assigns 18 hours to Ada and six to Sam. Neither exceeds the supplied period capacity. This separate workload check does not automatically prove the seven-day dependency schedule is feasible.

See the exact demonstration inputs
people
Person,AvailableHours
Ada,20
Sam,10
items
Task,Hours
Build package,12
Review package,6
Release preparation,6
Load this case into Team workload allocation ↗

Make the handoff explicit

Review the assumptions before adapting these figures. A calculated result is not an order, invitation, accepted quotation or guaranteed deadline. Save your own copy before leaving; no work is stored automatically.

See the workflow ↗